Project Description

Mosaic, Energy Enhancement Cogeneration Project, Mulberry, Florida
Responsible as the Lead Engineer in the preparation of a FEED package for the installation of a new Steam Turbine Generator (50MW), 13.8kV-69kV 50MW Main Substation, and three Heat Recovery Systems (HRS). Project consisted of preparation of capital cost and man hour estimates, one-line diagrams, generator controls, relay protection, specifications and layout of TG Auxiliaries and Step-up Substation (50MVA, 13.8kV – 69kV Transformer).

Project Details

Categories: